LONDON TUBE STATION & DLR IMPROVEMENTS DELAYED BY UP TO TWO YEARS - FEATHERSTONE

12.01.00am GMT Fri 12th Nov 2004

New information revealed by the London Assembly Liberal Democrats today shows that numerous Tube station improvements and Dockland Light Railway railcar refurbishments across the capital are being delayed or scaled back.

The information, revealed in papers that are to be discussed by the Transport for London Finance Committee later today (Friday) shows that:

· Nine Tube station refurbishments have been delayed between one month and 2 years

· Kings Cross Redevelopment work is a year behind schedule and will not be completed until after the Eurostar terminal is finished

· There is a 45% cut in the number of DLR trains being refurbished this year

· Greenwich Waterfront Transit will be delayed by at least 9 months

· Acton Town Tube redevelopment on hold awaiting renegotiation

Liberal Democrat Transport Spokesperson and Chair of the London Assembly Transport Committee, Lynne Featherstone, said:-

"With the Mayor increasing fares above the rate of inflation, people should rightly expect run down Tube Stations to be spruced up in the timescale they were promised.

"Investment in our crumbling transport infrastructure is welcome, but unless transport users start to see real improvements in the quality of the services, then they will begin to question why they are paying increased fares.

"It is vital that Transport for London ensures that as much as possible is done so that redevelopment and refurbishment work is done in time and on budget."

ENDS

Notes to editor

The information is taken from Transport For London, Finance Committee AGENDA ITEM 7a that will be discussed on Friday 12th November 2004 at 10.00 in the Boardroom, 14th Floor, Windsor House, 42-50 Victoria Street, London SW1H 0TL

Abstracts in quotes are taken from the Board Papers:-

· Camden Town redevelopment delayed by at least 3 months:-

"The Camden Town Congestion Relief Scheme Transport & Work Act public inquiry was completed in June 2004. The Inspector is considering planning for both the planning application due to the local authorities' recommendation for refusal with reference to the overstation development design, and the element under the Transport and Works Act. A Ministerial decision is still expected in Spring 2005."

· Covent Garden Tube station upgrade delayed by 2 years:-

"There has been significant slippage from March 2005 to early 2007 on the Covent Garden scheme to reconfigure the ticket hall and provide additional gate line capacity, associated with the need to obtain vacant possession of a tenancy, which is now expected to entail court proceedings. "

· Kings Cross Phase 1 upgrade delayed by a year:-

"Work has centred on continuing construction activities for Phase I works, and reviewing the impacts (physical, financial and contractual) of the deferral of Phase II. Phase 1 is currently forecast for completion on 18 September 2006, a year beyond target."

· Kings Cross Phase II delayed indefinitely, but even if work restarts and is completed it will be a year behind schedule and will not be built in time for Eurostar completion:-

"Government Ministers have ordered a review of Phase II of the project as a result of 2004/05 budget constraints and the latest out-turn forecast exceeding the overall budget. Should Phase II be re-started in 2005, completion could be achieved by mid 2008."

· 7 Tube stations refurbishments delayed between 1 and 4 months because of PPP:-

"Modernisation/refurbishment of Tufnell Park, Burnt Oak, Northfields and South Harrow stations are delayed by 2-4 months from January 2005. These were amongst the first projects to be started under the PPP and this led to prolonged discussions on scope and difficulties with assurance requirements."

And

"Completion of refurbishments at Dagenham Heathway, Turnham Green and North Harrow stations is delayed by between 1 and 4 months."

· Acton Town Tube refurbishment renegotiated, and delayed :-

"The completion date for Acton Town station refurbishment is being renegotiated."

· Delays in DLR railcar refurbishment. 45% cut in the number completed by the end of the year

"The latest forecast now anticipates 29 vehicles (as opposed to the original budget of 52) will be completed by the end of the year."

· Greenwich Waterfront Transit delayed by 9 months:-

"The programme has been delayed by results of the public consultation and rejection by LB Greenwich. Further consultation and safeguarding will add 9 months to the programme"

Bookmark this story at: del.icio.us Digg Facebook LibDig reddit StumbleUpon
Print this news story
Comment on this news story
Previous news story: BLAIR'S DECISION ON SYLVESTER CASE PREMATURE - FEATHERSTONE (Thu 11th Nov 2004).
Next news story: MORE THAN 150MILLION FARES DODGED IN LONDON SINCE LIVINGSTONE TOOK OFFICE (Tue 16th Nov 2004).

Related News Stories:

Thu 11th Feb 2010:

Wed 9th May 2007:

Wed 17th May 2006:

Thu 6th Oct 2005:

Thu 15th Sep 2005:

Thu 11th Aug 2005:

Wed 27th Jul 2005:

Mon 27th Jun 2005:

Sun 19th Jun 2005:

Wed 1st Jun 2005:

Tue 24th May 2005:

Mon 16th May 2005:

Fri 18th Mar 2005:

Wed 22nd Dec 2004:

Mon 18th Oct 2004:

Thu 16th Sep 2004:

Tue 27th Jul 2004:

Fri 2nd Jul 2004:

Related Press Articles:

Tue 5th Jan 2010:

Thu 17th Dec 2009:

Mon 16th Nov 2009:

Printed and hosted by Prater Raines Ltd, 98 Sandgate High Street, Folkestone CT20 3BY.
Published and promoted by London Assembly Liberal Democrats, City Hall, The Queen's Walk, London SE1 2AA.
The views expressed are those of the party, not of the service provider.